Variances and Components Reference > Variances by Transaction Flow
  PPT
Variances by Transaction Flow
 
Variances by Transaction Flow
PO Receipts
Purchase Price Variance
[PO Unit Cost(GL Unit CostOH)] * PO Qty Received
Subcontract Rate Variance
(Subcontract PO Unit CostSubcontract Unit Cost from Routing) * Qty Received
Receiver Matching
Accounts Payable Rate Variance
(Invoice Unit CostPO Unit Cost) * Invoice Quantity
Accounts Payable Usage Variance
(Invoice QtyPO Receipt Qty) * PO Unit Cost
Work Order Component Issue
Material Rate Variance
(WO BOM Unit Cost at IssueGL Unit Cost) * Actual Qty Issued
Labor Feedback
Labor Rate Variance
[(Actual Setup RateStd Setup Rate) * Actual Setup Hrs] + [(Actual Run RateStd Run Rate) * Actual Run Hrs]
Labor Usage Variance
[(Actual Setup HrsStd Setup Hrs) * Std Setup Rate] + [(Actual Run Hrs*Std Run Hrs) * Std Run Rate]
*Std Run Hrs = Std Run Hrs * (Qty Completed + Qty Rejected)
Burden Rate Variance
[(Actual Setup BdnStd Setup Bdn) * Actual Setup Hrs] +
[(Actual Run Bdn
Std Run Bdn) * Actual Run Hrs]
Burden Usage Variance
[(Act Setup HrsStd Setup Hrs) * Setup Bdn] + [(Act Run HrsStd Run Hrs) * Run Bdn]
Work Order Accounting Close
Subcontract Usage Variance
[Qty Received(Op Qty Completed + Op Qty Rejected)] * Subcontract Unit Cost from Routing
Material Usage Variance
{Actual Qty Issued[qty per * (qty completed + qty rejected)]} * GL Unit Cost
Method Variance