Study Questions
  PPT
Study Questions
Study Questions
1 Explain the difference between the three MRP planning modes available in QAD Enterprise Applications.
2 Give an example of what types of items would have the following setups:
 
Item Planning Maintenance
Set A
 
Set B
 
Master Sched
Yes
Master Sched
No
Plan Orders
No
Plan Orders
Yes
Time Fence
0
Time Fence
 
3 What MRP Item Planning data field would ensure that a planned order would never be less than 100 units?
 
4 What MRP order policy ensures a planned replenishment for every requirement after netting?
 
5 A sales order, for MRP purposes, is treated as dependent demand.
True False
6 MRP calculates the release or start date of a planned order by subtracting the appropriate lead time from the order due or need date.
True False
7 Accuracy in the BOM is not of critical importance since MRP is a planning tool.
True False
8 MRP automatically reschedules firm planned orders as long as the regenerative mode is selected.
True False
9 Specifying a yield percentage for an item has no effect on MRP planning activity.
True False