Roll Up Product Structure Costs
Product Structure Cost Roll-Up (13.12.13) is used to update the costs of parent items based on the costs of their lower-level components.
Product Structure Cost Roll Up (13.12.13)
Set Cost Update Field for All/Changed Only
• If All, this field is set to the run date for all parts
• If Changed Only, this field is set to the run date for items where costs have actually changed. This option gives better audit trail of dates when costs changed.
Include Yield %
Determines whether yield percentages from Routing Maintenance (14.13.1) are used to calculate component item costs. If set to Yes, component costs are adjusted to account for any yield percentage. This adjustment can be upwards (yield < 100%) or downwards (yield > 100%).
Note: If Scrap in Product Structure Maintenance (13.1) is set to a value other than 0.00%, the system adds those costs to the parent material cost lower level. Yield and scrap are separate values. If both are used, both will be calculated into the parent costs.
Item/Product Line/Item Type/Group
Use these fields to select the cost data to be rolled up. Leaving fields blank selects all in the category.
As of Date
The effective date to use when selecting which parent/component relationship to display. The default is the system date.
Low Level Costs (Material, Labor, Burden, Overhead, Subcontract)
Set these fields to Yes to include lower-level costs in the cost roll-up.
Product Structure Cost Report
Product Structure Cost Report (13.12.4) shows costs for an item and its components by structure level.