Planning > Example
  PPT
Example
This section provides an example of how the planning process works. In this example, QMI:
Enters a forecast for medical ultrasound units
Enters a sales order that consumes demand
Line 1: normal SO, quantity = 5, due in two weeks
Line 2: abnormal SO, quantity = 5, due in five weeks
Runs MRP
Approves planned purchase orders
Creates a purchase order using MRP requisitions for the component items
Receives the PO
Approves planned work orders
Releases and issues work order
Builds work order items and puts the items into stock
Ships a sales order
In the process of reviewing the production schedule and MRP reports, you will see the effect of the manufacture and purchase lead times on release dates for the purchase orders and work orders in the example.