Report Labor
On the shop floor, Angela (employee 10-EMP01) uses Labor Feedback by Work Order (16.20.1) to report the labor for completing the 22 medical ultrasound units. Operation 30, shown here, is the last operation.
Each operation was recorded with Operation Complete selected. This means no intermediate reporting was done. Move Next Operation was selected, which set the status at the next operation to Queue. Previous Operations Complete was selected just to be sure all operations were closed in case anyone forgot to report it.
Discussion
Where were the standard setup and run times defined?