1 Using Item-Warehouse Maintenance change the sample quantity to 25 for item 03120.
2 Use Receipts-Unplanned to receive: 100 EA, item 03120
What loads are created? View Inventory Detail Inquiry to determine the LPN, item, and quantity. Note the parameters here:
 
 
LPN
Item
Quantity
 
 
 
 
 
 
There should be two loads both with the same LPN. One for 25 the other for 75 each with a pending move. Where is each load scheduled for movement? Note the parameters here:
 
 
 
LPN
Item
Quantity
Move To
 
 
 
 
 
 
 
 
Did the inventory status of both loads change to the status you defined using Inventory Status Change Maintenance?
3 Use Movement Confirmation Workbench to complete all moves.
4 Confirm a successful inspection using either Sample Inspection Maintenance or Sample Inspection Workbench.
The load in inspection should have a pending move back into storage. Where is the load scheduled for movement? Note the parameters here:
 
 
 
LPN
Item
Quantity
Move To
 
 
 
 
 
 
 
 
Did the inventory status of both loads change to the status you defined using Inventory Status Change Maintenance?
5 Use Movement Confirmation Workbench to complete all moves.
What is the new inventory position of the load? Note the parameters here:
 
 
 
LPN
Item
Quantity
Move To
 
 
 
 
 
 
 
 
If done successfully, the load should be moved back to pallet storage and merged with the original LPN. The new load quantity is 100.