Family-Level Planning > Maintaining Family Plans
  
Maintaining Family Plans
After you consolidate, review the family plan and verify the production due quantities against available resource capacity. Adjust production due as necessary.
Operations Plan Resource Inquiry (33.15.21) displays projected resource load for the family plan production due quantity.

Operations Plan Resource Inquiry (33.15.21)
Item Number
Enter the item number. To review resource load for all items that use this resource, leave blank.
Site
Enter the site code.
Resource
Enter the code of the critical resource to review.
Start
Enter the start date for reviewing information. The default start date is Monday of the current week.
End
Enter the end date for including information. The default end date is blank.
Per
Enter the multiple to use for resource load calculations. By default, the system calculates resource load based on actual available workdays and resource capacity (Per = 1). But you can reset this multiple to see how load would balance against additional capacity. The formula is:
(Production Due * Resource Quantity Per) ÷ Per * (Workdays * Resource Capacity)
Output
Enter the output for the report—terminal, printer, or ASCII file name.
Click Next to view the output.
Workdays
The number of days in the shop calendar week, as defined in Calendar Maintenance (36.2.5).
Capacity
The weekly capacity for the resource, calculated as:
Workdays in the Weekly Shop Calendar * Daily Resource Capacity
The shop calendar is defined in Calendar Maintenance (36.2.5). Resource capacity is defined in Resource Maintenance (21.1).
Load
The weekly production load for the specified resource, calculated as:
Production Due Quantity * Resource Quantity Per
You can adjust production due in Operations Plan Maintenance (33.15.1). Resource quantity per is defined in Item Resource Bill Maintenance (21.17).
Over/Under
Each week’s capacity shortages and availability, calculated as:
Capacity – Load
Note: Negative figures denote shortages and positive figures denote available capacity.
Cumulative
The total capacity shortage or availability for the resource. This number varies, based on the start date you specify.