Advanced Repetitive > Setting Up Advanced Repetitive > Setting Up Changeover Times
  
Setting Up Changeover Times
Define changeover times for a production line in Line Changeover Maintenance (18.22.1.6). For the system to work correctly, you should define changeover times between each pair of items. For instance, on a line where red, green, and gray items are manufactured, the changeover time can vary depending on whether red is being switched to green or to gray.
Example: If a line manufactures three items—A, B, and C—define changeover times for each of the following.
 
From
To
A
B
B
A
A
C
C
A
B
C
C
A
A large number of changeover times might be more effectively managed outside of the system using spreadsheet software. Use the CIM interface programs to load the data into Line Changeover Maintenance.
See User Guide: QAD System Administration for details on CIM.