Periodic Costing Adjustments > Adjustment Programs > Uploading Unit or Total Cost Adjustments
  
Uploading Unit or Total Cost Adjustments
When you make adjustments, use one of the two following programs to upload the adjustment to Periodic Costing:
PC Total Cost Adjustment Upload (30.5.5.5)
PC Unit Cost Adjustment Upload (30.5.5.4)
You enter the XML file with schema to upload the adjustments; then press Go. For information on the XML file, see Loading Work Center Rates from XML.
You find the rate or total for each cost center, then upload the actuals for labor and burden for each individual work center.
The following depicts the adjustment upload program for PC total cost adjustment, but the screen is similar for the upload program for PC unit cost adjustment.

PC Total Cost Adjustment Upload (30.5.5.4)