Study Questions
1 Explain the meaning of “operations are back-scheduled from the MRP due date.”
2 Explain the Dispatch Report.
3 Give an example of non-productive labor feedback.
4 All planned orders are automatically scheduled by MRP with respect to their release and due dates.
True False
5 The Move Next Operation field is set to Yes in the Shop Floor Control File. This setting places the operation in setup (S) status.
True False
6 MFG/PRO tracks the quantity completed at each operation as the work order progresses through its routing.
True False
7 A purchase order line item with a Type field set to S refers to a subcontract operation.
True False
8 If you are tracking WIP, are employee records required?
9 Do holidays always impact the entire site?
10 What is the impact of not posting variances in Shop Floor Control?