Adjusting Capacity and Load
If a work center or machine is over- or under-loaded, you can modify either its capacity or the timing or amount of the load.
Adjusting Capacity
Adjust capacity using calendar maintenance and exception functions, which are described in QAD System Administration User Guide.
Add or subtract workday hours as needed for work center or shop calendars.
Adjusting Load
Adjust the timing or amount of load by modifying:
Work order due dates
Operation lead time components
Repetitive schedules
Note: If you manually adjust operation start or stop dates, CRP reschedules them the next time it is run.