Panel/Frame
|
Object
|
Indicator
|
Meaning
|
|
Resource Panel
|
Resources
|
The resource includes one or more items with a supply shortage (negative POH).
|
|
|
MSW Capacity Panel
|
Remaining capacity
|
The planned capacity was consumed from prior days, to satisfy the required capacity needs of the date column highlighted in yellow.
|
|
|
Period Available Capacity
|
|
• Period available capacity is less than or equal to 0 for every day prior to this date.
AND
• Required capacity is greater than capacity.
|
|
|
|
|
• Excess capacity for the day is consumed by a future shortage.
• The system consumes excess capacity from a prior day.
|
|
|
MSW Schedule Grid and Supply/Demand Panel
|
Item number
|
Projected on-hand is less than 0 (zero) within the firm scheduling horizon.
|
|
|
|
Projected On-Hand
|
Projected on-hand is less than safety stock value plus seasonal demand within the firm scheduling horizon.
|
|
|
|
|
Projected on-hand is negative within firm schedule period.
Alternate production lines without active orders are not colored for POH. For example, when you have the same item on two production lines, and you schedule quantities on the first production line but not the second line, the system does not display colored schedule grid cells for the second production line.
|
|
|
|
|
|