Work Orders > Closing Work Orders > General Ledger Period End
  
General Ledger Period End
Since you can enter a GL effective date on work order, shop floor control, and repetitive transactions, a strict procedure is not required to account correctly for activity in the general ledger. Some reports, such as Work Order WIP Cost Report (16.3.5), are sensitive to period-end procedures. Use the following outline to write a procedure that fits your needs.
1 All work order, shop floor control, and repetitive transactions should be completed and reviewed before starting the new period, including the following:
Work Order Component Issues (16.10)
Work Order Receipts (16.11)
Work Order Receipt Backflush (16.12)
Work Order Operation Backflush (16.19)
Labor Feedback by Work Order (17.1), by Employee (17.2), by Work Center (17.3)
Operation Complete Transaction (17.5)
Repetitive Setup Transaction (18.13)
Repetitive Labor Transaction (18.14)
Non-Productive Labor Feedback (17.4)
2 The status of all closed work orders should be changed to Closed.
3 All open cumulative work orders in the Repetitive module should be changed to Closed.
4 Run WIP Material Cost Revaluation (16.22) to update allocated, released, and closed work orders.
5 Run Work Order Accounting Close (16.21) and Cumulative Order Accounting Close (18.9).
6 Print Work Order WIP Cost Report (16.3.5) and any other time-sensitive reports required.
7 After reviewing these reports, proceed with the new period.