Executing CRP
Generate capacity requirements for manufacturing orders using Recalculate Capacity Plan (24.1).
Note: Generally, you should run CRP after running MRP.
Recalculate Capacity Plan (24.1)
CRP determines capacities based on the available hours or machines for a work center or department. It multiplies working days, defined in the shop calendar, by work center machine capacity to calculate capacity per CRP reporting period.
CRP explodes the routings and processes for the orders you select. It then determines capacity requirements for selected manufacturing orders by scheduling their operations. CRP determines operation start and due dates using the work center and shop calendars and a technique called back scheduling.