Run MRP
The next step is to run MRP.
Three calculations are available in QAD Enterprise Applications:
1 Net Change Materials Plan (23.1)
Only calculates changes since the last MRP calculation
2 Regenerate Materials Plan (23.2)
Complete recalculation of all demand and supply
Required to run when the MRP is first used
3 Selective Materials Plan (23.3)
Calculates only manually selective factors