Use MRP and CRP > Regenerate Materials Plan
  PPT
Regenerate Materials Plan
Regenerate Materials Plan (23.2) recalculates demand and plans supply for all items in the site. This method generates a plan for all items, not just the items that have changed since the last run. The outputs of net change and regenerative MRP are the same. However, net change MRP generally runs faster than regenerative, since it only plans for items that changed since MRP was last run.
Guidelines:
Run MPR in regenerative mode the first time you use it.
Always schedule periodic regenerative MRP runs, even if you primarily use net change MRP, since net change MRP does not consider demand or forecast for items entering the MRP horizon over time.
For forecasting, it is useful to run MRP at 12:01 a.m. Monday.