Planning > Review Inquiries: Master Schedule Detail > MRP Summary Inquiry: Item 50001
  PPT
MRP Summary Inquiry: Item 50001
This slide shows the MRP Summary Inquiry (23.13) for component 50001 (Probe Unit).
Discussion
Why does QMI need 27 probes in week 04/16? Do you remember when the sales order line was due on the order created earlier?
The MRP Detail Inquiry may provide an answer.
MRP Detail Inquiry: Item 50001
The MRP Detail Inquiry (23.16) for item 5001 shows the impact of new requirements for the parent end-item (01010). The system is planning work orders to assemble the probes for the orders that QMI created.
More orders for a component may become due for release earlier and for larger quantities than you expect because of a combination of factors:
Sales orders are due in the middle of the week.
Forecasts are due on Mondays.
The lead time offset for assembly and purchase of components is combined.
Demands must be combined on one planed order because of the POQ policy.