Work Center and Routing Setup and Maintenance > Routing Cost Roll-Up
  PPT
Routing Cost Roll-Up
Each routing or process describes the steps required to make this item, including:
Where performed (Work Center)
How long (Queue Time, Setup Time, Run Time, Wait Time, and Move Time)
The expected Yield% at each operation
Cost roll-ups use this information to calculate the manufacturing costs, lead times, and total yield for the item
Note: Normally this function uses the current or simulated cost set.
Discussed in Training Guide: Product Costing and Cost Management.
These elements are used in calculating costs, yields, and lead times.
Routing Cost Roll-Up
This function calculates this-level costs. It can take a long time to process.
Note: Always run this function before Product Structure Cost Roll-Up when establishing standard costs.