Effect of Linking on Routing Cost Rollups
Routing Cost Roll-Up (14.13.13) calculates this-level manufacturing costs, lead times, and total yield for an item at a particular site.
If a GL standard cost set is specified for the rollup, then:
• The routing cost rollup does not update this-level costs if the item at the rollup site is linked.
• Lead time and yield for all selected items are calculated whether they are linked or not.
• The operation cost calculation recognizes linked costs.
• Updating the active GL standard costs at a cost source site automatically updates the costs at target sites.
Important: Routing Cost Roll-Up does not recognize links if the rollup is performed for current or simulation cost sets. In order to roll up costs correctly for linked items, you must use a GL standard cost set.