Set Up Process Shifts
Use Process Calendar Maintenance (17.1.13) to define the normal hours for each shift associated with a kanban process. You can also define any exceptions to that normal pattern using Process Calendar Except Maint (17.1.14). Additionally, define full-day exceptions in Process Non-Workday Update (17.1.25). For information on setting up shop calendars, see QAD System Administration User Guide.
System calculations use process calendar records to determine the amount of time available. For example, when you update process data using Basic Process Calculations (17.2.3), the system examines calendar records during the specified period to calculate the available time for each work day. See Perform Process Calculations.

Process Calendar Maintenance (17.1.13)
You can define up to four shifts for each day of the week. A working day should have at least one shift with some number of hours greater than zero.
The hours per shift is the number of hours the shift is capable of producing, rather than the total number of working hours for the shift.
Note: Although—because of shift overlaps—the total number of hours for all shifts can exceed 24, this is not recommended. It can result in invalid system calculations.
The hours worked by a particular shift can change because of holidays, planned shutdowns, or periods with planned overtime. Manage exceptions by specifying adjustment hours to shifts by effective date. When you run Preliminary Level Schedule Report (17.14.2) or Level Mix Workbench (17.14.1) for a process, you can specify the reference codes associated with these exceptions. The system adjusts available production time as appropriate and displays each code and the associated number of hours in an individual column.
See Preliminary Level Schedule Report and Level Mix Workbench.