Modifying Production Order Quantities
You can manually adjust the production order quantity in PSW. When you change the quantity of a production order, PSW applies the quantity change to the entire order, not a specific operation.
1 Select a production order on the Sequence Grid.
The system highlights the selected production order.
2 Modify the value in the Quantity Ordered column by double-clicking in the cell.
PSW updates all calculations. Color indicators may change in the MSW.
Note: You can also change the quantity using Production Order Maintenance within PSW.