Resource Relationships Tab
This shows the production lines or work centers that are associated with the MSW/PSW resource in context. The resource in context is the particular resource you select in the MSW/PSW either from the Navigator or by clicking a row in the Schedule Grid. For a resource in context:
• When it is a production line, then its related work centers are listed. This relationship is established because production lines reference work orders, and work order routing details reference work centers.
• When it is a work center, then its related production lines are listed. This relation is established because work centers reference work order routing details, and work orders reference production lines.
This information lets you know which resources might be affected when there are EAM work orders for a related resource.
In the following screenshot, the production line bgprod is in context and the work centers that are associated to it are listed below.
.
Resource Relationships Tab