QAD 2017 Enterprise Edition > User Guides > Warehousing > Algorithms > Algorithm Listings > Shortage-Clearance Algorithms
  
Shortage-Clearance Algorithms
Shortage-Clearance Algorithms lists the shortage-clearance algorithms that are supplied with the system.

Shortage-Clearance Algorithms
 
 
Algorithm
Description
1
Sales Order Clearance by Priority by Due Date
Clears short sales orders, highest priority first.
2
Sales Order Clearance by Due Date by Priority
Clears short sales orders, earliest due date first.
11
Work Order Clearance by Priority by Due Date
Clears short work orders, highest priority first.
12
Work Order Clearance by Due Date by Priority
Clears short work orders, earliest due date first.
21
Distribution Order Clearance by Priority by Due Date
Clears short distribution orders, highest priority first.
22
Distribution Order Clearance by Due Date by Priority
Clears short distribution orders, earliest due date first.
31
Unplanned Issue Clearance by Priority by Due Date
Clears short unplanned issues, highest priority first.
32
Unplanned Issue Clearance by Due Date by Priority
Clears short unplanned issues, earliest due date first.
41
Global Clearance by Priority by Due Date
Clears shortages regardless of order type, highest priority first.
42
Global Clearance by Due Date by Priority
Clears shortages regardless of order type, earliest due date first.