Algorithm
|
Description
|
|
1
|
Sales Order Clearance by Priority by Due Date
|
Clears short sales orders, highest priority first.
|
|
2
|
Sales Order Clearance by Due Date by Priority
|
Clears short sales orders, earliest due date first.
|
|
11
|
Work Order Clearance by Priority by Due Date
|
Clears short work orders, highest priority first.
|
|
12
|
Work Order Clearance by Due Date by Priority
|
Clears short work orders, earliest due date first.
|
|
21
|
Distribution Order Clearance by Priority by Due Date
|
Clears short distribution orders, highest priority first.
|
|
22
|
Distribution Order Clearance by Due Date by Priority
|
Clears short distribution orders, earliest due date first.
|
|
31
|
Unplanned Issue Clearance by Priority by Due Date
|
Clears short unplanned issues, highest priority first.
|
|
32
|
Unplanned Issue Clearance by Due Date by Priority
|
Clears short unplanned issues, earliest due date first.
|
|
41
|
Global Clearance by Priority by Due Date
|
Clears shortages regardless of order type, highest priority first.
|
|
42
|
Global Clearance by Due Date by Priority
|
Clears shortages regardless of order type, earliest due date first.
|