Use MRP and CRP > Review MRP Information > Past Due Receipts
  PPT
Past Due Receipts
Past Due Receipts Inquiry
Past Due Receipts Inquiry (23.19) shows you past due receipts.
Because the projected quantity on hand value uses released order due dates for supply, orders that become past due are a real problem. It is imperative that past due orders be rescheduled with a due date in the future for the projected quantity on hand value to be meaningful.
MRP has no logic to deal with past due orders, they are lumped into the first column of the summary inquiry screen as past due.
Calculate the Capacity Plan
Once the MRP has been reviewed and action messages acted upon, the capacity plan can be run. The MRP output is the direct input to CRP. Capacity Requirements Planning uses all work orders on the system to calculate the load.
All capacity planning and reporting is organized around work center/machine.