Data Collection > Maintaining Loaded Data > Changing Production Data
  
Changing Production Data
To change previously loaded production due or actual production quantities, use Production Data Maintenance (33.13.21). You can also use this program (manually or with CIM) to record production quantities.
See User Guide: QAD System Administration for information on CIM.
By default, the screen displays item information in calendar weeks, but you can switch to GL periods.
Warning If you normally plan in weeks, do not change quantities in period view. If you do, the system permanently reassigns all weekly quantities to the first week of each period.

Production Data Maintenance (33.13.21)
This function is very similar to Sales Data Maintenance (33.13.13). Only two fields are different:
Production Due
Enter the production due quantity to update.
Actual Production
Enter the actual production quantity to update. You can update this only in
week view. In period view, the system cannot associate quantities back to the correct week.
See Changing Sales Data.
Important: If you record or change production due quantities for the operations plan, you must set Calculate Production Due to No when you run Source Matrix Explosion (33.13.8). Otherwise, the explosion will overwrite your changes.