How to calculate MRP action message suggested due date?
David Guan, modified 3 Years ago.
How to calculate MRP action message suggested due date?
Post Date: 3/14/18 (Bronze, 5 Posts) Recent PostsWe met a MRP detail export from 23.16.4 as below, i want to know how to calculate the suggested due date for open PO dvtest line 2.
xxmrmpiq01.p 23.16.4 物料需求計畫明細查詢(原23.16)* 03/14/18
料品號: 30G11-WC25637-001 廠別: 1100 開始日期:
PUSH SWITCH(RoHS) 按壓開關(RoHS) 輸出: text
料品號: 30G11-WC25637-001 現存數量: 1,583.0 廠別: 1100
PUSH SWITCH(RoHS) 按壓開關(RoHS) 計: EA 採購/生產: P
採購員/計劃員: ypurbqm 訂購政: POQ 最小訂量: 500 製造前: 0
主排程: Y-是 訂購週期: 7 最大訂量: 0 採購前: 70
材料需求計劃: N-否 時界: 0 訂購倍量: 500 檢驗前: 0
計劃訂單: Y-是 安全時間: 5 訂單數量: 0 檢驗: N-否
發料政策: Y-是 安全庫位: 0 合格率: 100.00% 累計LT: 0
到期日期 Gross Reqs 計劃收料量 Proj QOH 計劃工單 明細
-------- ---------- ---------- ---------- ---------- -------------------------
1,583 期初可用量
03/15/18 48 1,535 工:XKU11128 ID:M259047
組裝: 00RM1-9732000-007
03/15/18 48 1,487 工:XKU11457 ID:M259520
組裝: 00RM1-9732000-007
03/15/18 48 1,439 工:XKU11024 ID:M258674
組裝: 00RM1-9732000-007
03/26/18 48 1,391 工:XKU11458 ID:M260314
組裝: 00RM1-9732000-007
03/26/18 100 1,291 工:XKU11458 ID:M260520
組裝: 00RM1-9802000-001
04/02/18 48 1,243 工:XKU11461 ID:M260912
組裝: 00RM1-9732000-007
04/09/18 48 1,195 工:XKU11462 ID:M261199
組裝: 00RM1-9732000-007
04/09/18 48 1,147 工:XKU11505 ID:M262316
組裝: 00RM1-9732000-007
04/09/18 48 1,099 工:XKU11462 ID:M261645
組裝: 00RM1-9732000-007
04/16/18 48 1,051 工:XKU11718 ID:M263282
組裝: 00RM1-9732000-007
04/16/18 48 1,003 工:XKU11688 ID:M263105
組裝: 00RM1-9732000-007
04/16/18 48 955 工:XKU11604 ID:M262720
組裝: 00RM1-9732000-007
04/23/18 48 907 工:XKU11876 ID:M263884
組裝: 00RM1-9732000-007
04/23/18 48 859 工:XKU11892 ID:M264096
組裝: 00RM1-9732000-007
04/23/18 48 811 工:XKU11813 ID:M263631
組裝: 00RM1-9732000-007
04/30/18 48 763 工:12160117 ID:2470076
組裝: 00RM1-9732000-007
04/30/18 48 715 工:09230080 ID:2222736
組裝: 00RM1-9732000-007
04/30/18 48 667 工:09230077 ID:2222733
組裝: 00RM1-9732000-007
05/08/18 48 619 工:12160116 ID:2470075
組裝: 00RM1-9732000-007
05/08/18 48 571 工:11041049 ID:2348607
組裝: 00RM1-9732000-007
05/15/18 48 523 工:12160120 ID:2470079
組裝: 00RM1-9732000-007
到期日期 Gross Reqs 計劃收料量 Proj QOH 計劃工單 明細
-------- ---------- ---------- ---------- ---------- -------------------------
05/15/18 48 475 工:12100031 ID:2455863
組裝: 00RM1-9732000-007
05/15/18 48 427 工:09230071 ID:2222727
組裝: 00RM1-9732000-007
05/22/18 48 379 工:12160125 ID:2470082
組裝: 00RM1-9732000-007
05/22/18 48 331 工:11280072 ID:2420992
組裝: 00RM1-9732000-007
05/29/18 48 283 工:12160124 ID:2470081
組裝: 00RM1-9732000-007
05/29/18 48 235 工:12160115 ID:2470074
組裝: 00RM1-9732000-007
06/05/18 48 187 工:12160118 ID:2470077
組裝: 00RM1-9732000-007
06/05/18 48 139 工:12160123 ID:2470080
組裝: 00RM1-9732000-007
06/05/18 48 91 工:11041021 ID:2348604
組裝: 00RM1-9732000-007
06/19/18 48 43 工:12160128 ID:2470085
組裝: 00RM1-9732000-007
06/19/18 48 -5 工:12160119 ID:2470078
組裝: 00RM1-9732000-007
06/19/18 48 -53 工:12160129 ID:2470086
組裝: 00RM1-9732000-007
06/26/18 48 -101 工:12300065 ID:2522750
組裝: 00RM1-9732000-007
07/03/18 48 -149 工:12300066 ID:2522751
組裝: 00RM1-9732000-007
07/10/18 48 -197 工:12160127 ID:2470084
組裝: 00RM1-9732000-007
07/10/18 48 -245 工:12160134 ID:2470089
組裝: 00RM1-9732000-007
07/24/18 48 -293 工:01270067 ID:2601175
組裝: 00RM1-9732000-007
07/24/18 48 -341 工:12160126 ID:2470083
組裝: 00RM1-9732000-007
07/24/18 300 -41 採: dvtest 項次: 1
07/24/18 459 500 工:03140002 ID:2702706
發放日期 05/15/18
07/31/18 48 411 工:01270071 ID:2601179
組裝: 00RM1-9732000-007
07/31/18 48 363 工:01270070 ID:2601178
組裝: 00RM1-9732000-007
07/31/18 48 315 工:12160131 ID:2470087
組裝: 00RM1-9732000-007
08/07/18 48 267 工:01270068 ID:2601176
組裝: 00RM1-9732000-007
08/07/18 48 219 工:01270069 ID:2601177
組裝: 00RM1-9732000-007
08/14/18 48 171 工:02270107 ID:2658321
組裝: 00RM1-9732000-007
08/14/18 48 123 工:01270072 ID:2601180
組裝: 00RM1-9732000-007
08/21/18 100 23 工:09230650 ID:2222828
組裝: 00RM1-9802000-001
到期日期 Gross Reqs 計劃收料量 Proj QOH 計劃工單 明細
-------- ---------- ---------- ---------- ---------- -------------------------
08/21/18 48 -25 工:02270117 ID:2658323
組裝: 00RM1-9732000-007
08/21/18 48 -73 工:02270108 ID:2658322
組裝: 00RM1-9732000-007
08/21/18 427 500 工:03140003 ID:2702707
發放日期 06/12/18
08/25/18 120 547 採: dvtest 項次: 2
08/28/18 48 499 工:02270119 ID:2658325
組裝: 00RM1-9732000-007
08/28/18 48 451 工:02270118 ID:2658324
組裝: 00RM1-9732000-007
09/04/18 48 403 工:02270120 ID:2658326
組裝: 00RM1-9732000-007
09/04/18 48 355 工:02270125 ID:2658327
組裝: 00RM1-9732000-007
09/11/18 48 307 工:02270126 ID:2658328
組裝: 00RM1-9732000-007
09/11/18 48 259 工:02270128 ID:2658330
組裝: 00RM1-9732000-007
09/11/18 48 211 工:02270127 ID:2658329
組裝: 00RM1-9732000-007
09/17/18 100 111 工:12100052 ID:2455881
組裝: 00RM1-9802000-001
09/20/18 48 63 工:02270130 ID:2658332
組裝: 00RM1-9732000-007
09/20/18 48 15 工:02270129 ID:2658331
組裝: 00RM1-9732000-007
Raymond Chin Kwie Joe, modified 8 Years ago.
Re: How to calculate MRP action message suggested due date?
Post Date: 3/14/18 (Rhodium, 825 Posts) Recent PostsPhill Norrey, modified 8 Years ago.
Re: How to calculate MRP action message suggested due date?
Post Date: 3/14/18 (Yoda, 1010 Posts) Recent PostsFirstly you are looking at a custom version of the mrp inquiry.
However this report was never intended for the purpose you are asking about.
If you look at 23.6 or 23.7 then you will see if MRP has recommended a new Due Date. You will NEVER get a suggested date for an actual PO as you have already made the order so MRP will just make an action message telling you to expidite or de-expidite the order.
If you can explain more about what you are trying to do I will be able to give you more details
David Guan, modified 8 Years ago.
Re: How to calculate MRP action message suggested due date?
Post Date: 3/15/18 (Bronze, 5 Posts) Recent PostsDear Raymond and Phil,
Thanks for your reply!
Yes , MRP make an action message tell me to expedite the PO dvtest Line 2 and suggest me to advance the due date to 7/17/2018, I want to know how MRP to calculate the suggested due date and why advance to 7/17/2018 and not 7/16/2018?
Below is the action message, thank you!
xxmrmprp02.p 23.8.7 MRP Action Message* Date: 03/14/18
page: 1 Karrie HK Time: 19:09:28
Item Number Date Action Message Detail Order Number Line/ID Quantity Due Date
------------------ -------- --------------------------- ------------ -------- ---------- --------
30G11-WC25637-001 06/11/18 expedite purchase order dvtest 1 300.0 07/24/18
30G11-WC25637-001 07/17/18 expedite purchase order dvtest 2 120.0 08/25/18
The 23.16.4 heqading in english as below for you reference.
xxmrmpiq01.p 23.16.4 MRP Detail Inquiry(原23.16)* 03/14/18
Item Number: 30G11-WC25637-001 site: 1100 Start Date:
PUSH SWITCH(RoHS) 按壓開關(RoHS) output: text
Item Number: 30G11-WC25637-001 Qty On Hand: 1,583.0 site: 1100
PUSH SWITCH(RoHS) 按壓開關(RoHS) UM: EA P/M: P
Buyer/Planner: ypurbqm Order policy : POQ Minimum Qty: 500 MFG LT: 0
Mstr Sched: YES Order Period: 7 Maximum Qty: 0 Pur LT: 70
MRP Required : NO Time Fence : 0 MPQ: 500 Ins LT: 0
Plan Orders: YES Safety Time: 5 Order Qty: 0 Inspect: NO
Issue Policy: YES Safety Stock: 0 Yield%: 100.00% Cum LT: 0
Raymond Chin Kwie Joe, modified 8 Years ago.
Re: How to calculate MRP action message suggested due date?
Post Date: 3/15/18 (Rhodium, 825 Posts) Recent PostsPhill Norrey, modified 8 Years ago.
Re: How to calculate MRP action message suggested due date?
Post Date: 3/15/18 (Yoda, 1010 Posts) Recent PostsOK the answer is actually quite simple. You have a Safety LT of 5 days. In QAD that is actually working days so it equates to 7 calendar days.
MRP will ALWAYS suggest you move existing orders before creating new Orders so if we follow the logic of the action messages it firstly tells you to move Line 1 of the PO to 06/11. If you did that then you would not go negative again until 07/24. So it wants to pull the second line forward as well to ensure you don't go negative and because you have 7 calendar days Safety LT it means you need to receive it (DUE Date) 7/17.
| due | demand | supply | Proj QOH | |
| 5-Jun | 48 | 0 | 187 | |
| 5-Jun | 48 | 0 | 139 | |
| 5-Jun | 48 | 0 | 91 | |
| 11-Jun | 300 | 391 | dvtest ln 1 | |
| 19-Jun | 48 | 0 | 343 | |
| 19-Jun | 48 | 0 | 295 | |
| 19-Jun | 48 | 0 | 247 | |
| 26-Jun | 48 | 0 | 199 | |
| 3-Jul | 48 | 0 | 151 | |
| 10-Jul | 48 | 0 | 103 | |
| 10-Jul | 48 | 0 | 55 | |
| 17-Jul | 120 | 175 | dvtest ln2 | |
| 24-Jul | 48 | 0 | 127 | |
| 24-Jul | 48 | 0 | 79 |
David Guan, modified 8 Years ago.
Re: How to calculate MRP action message suggested due date?
Post Date: 3/18/18 (Bronze, 5 Posts) Recent PostsDear Raymond and Phill,
Thanks for your reply!
MRP will ALWAYS suggest you move existing orders before creating new Orders,
First time Project-Qty-OnHand go negative is 6/19/2018, so MRP suggest us move PO Dvtest Line 1 to 6/18/2018 prior 6/19/2018,
and the suggest date is 6/11/2018 due to 7 calendars safety time .
And second time Project-Qty-OnHand go negative is 7/24/2018, so MRP suggest us move the second supply PO Dvtest Line 2 to 7/23/2018,
and the suggest date should is 7/16/2018 due to 7 calendars safety time, but it is 7/17/2018.
i would like to know the why is 7/17/2018 not 7/16/2018. thanks!
Raymond Chin Kwie Joe, modified 8 Years ago.
Re: How to calculate MRP action message suggested due date?
Post Date: 3/19/18 (Rhodium, 825 Posts) Recent Posts@Phil: good calculation!I
Regarding the question, I think Phil answered this, if you take the 24th then thedate is the 17th.Probablythe 23rd is suggested because the 24th of July is a saturday. If you move the supply to the 23rd it may well suggest the 16th. btw, if you want to understand these mechanisms you will have to read & practice. Unless you have a Phil around to help you :-)
David Guan, modified 8 Years ago.
Re: How to calculate MRP action message suggested due date?
Post Date: 3/20/18 (Bronze, 5 Posts) Recent PostsDear Raymond and Phill,
Thanks for your help for this topic!
7/24/2018 is not saturday.
There are two demand in 7/24/2018, and the supply can satify the first demand but can not satify the second,
so maybe the MRP calculate the suggested due date is start from 7/24/2018, and move it forward 7 calendar days to 7/17/2018.
Phill Norrey, modified 8 Years ago.
Re: How to calculate MRP action message suggested due date?
Post Date: 3/21/18 (Yoda, 1010 Posts) Recent PostsSometimes following dates can be complicated. Do you have any holidays set up in your calendar for example.
What I would suggest is that you first remove the SLT so you can see the actual calculation for due dates with no interferance. This should help make it easier to understand.
And then change it to one day and run again. Repeat this until you get to your back to your 5 working day SLT.
It is complicated because of the caculation to change from work days to calendar days co by doing it one at a time you will see what happens
David Guan, modified 8 Years ago.
Re: How to calculate MRP action message suggested due date?
Post Date: 4/9/18 (Bronze, 5 Posts) Recent PostsDear Phill and Raymond,
With your help, my MRP problem has been solved, thank you very much!