How to calculate MRP action message suggested due date?

David Guan, modified 3 Years ago.

How to calculate MRP action message suggested due date?

Post Date: 3/14/18 (Bronze, 5 Posts) Recent Posts

We met a MRP detail export from 23.16.4 as below, i want to know how to calculate the suggested due date for open PO dvtest line 2.

xxmrmpiq01.p          23.16.4 物料需求計畫明細查詢(原23.16)*          03/14/18


      料品號: 30G11-WC25637-001   廠別: 1100        開始日期:
 PUSH SWITCH(RoHS)        按壓開關(RoHS)                       輸出: text

       料品號: 30G11-WC25637-001         現存數量: 1,583.0      廠別: 1100
PUSH SWITCH(RoHS) 按壓開關(RoHS)               計: EA      採購/生產: P
採購員/計劃員: ypurbqm   訂購政: POQ     最小訂量: 500        製造前: 0
       主排程: Y-是    訂購週期: 7       最大訂量: 0          採購前: 70
 材料需求計劃: N-否        時界: 0       訂購倍量: 500        檢驗前: 0
     計劃訂單: Y-是    安全時間: 5       訂單數量: 0            檢驗: N-否
     發料政策: Y-是    安全庫位: 0         合格率: 100.00%    累計LT: 0

到期日期 Gross Reqs 計劃收料量   Proj QOH   計劃工單 明細
-------- ---------- ---------- ---------- ---------- -------------------------
                                    1,583            期初可用量
03/15/18         48                 1,535            工:XKU11128 ID:M259047
                                                     組裝: 00RM1-9732000-007
03/15/18         48                 1,487            工:XKU11457 ID:M259520
                                                     組裝: 00RM1-9732000-007
03/15/18         48                 1,439            工:XKU11024 ID:M258674
                                                     組裝: 00RM1-9732000-007
03/26/18         48                 1,391            工:XKU11458 ID:M260314
                                                     組裝: 00RM1-9732000-007
03/26/18        100                 1,291            工:XKU11458 ID:M260520
                                                     組裝: 00RM1-9802000-001
04/02/18         48                 1,243            工:XKU11461 ID:M260912
                                                     組裝: 00RM1-9732000-007
04/09/18         48                 1,195            工:XKU11462 ID:M261199
                                                     組裝: 00RM1-9732000-007
04/09/18         48                 1,147            工:XKU11505 ID:M262316
                                                     組裝: 00RM1-9732000-007
04/09/18         48                 1,099            工:XKU11462 ID:M261645
                                                     組裝: 00RM1-9732000-007
04/16/18         48                 1,051            工:XKU11718 ID:M263282
                                                     組裝: 00RM1-9732000-007
04/16/18         48                 1,003            工:XKU11688 ID:M263105
                                                     組裝: 00RM1-9732000-007
04/16/18         48                   955            工:XKU11604 ID:M262720
                                                     組裝: 00RM1-9732000-007
04/23/18         48                   907            工:XKU11876 ID:M263884
                                                     組裝: 00RM1-9732000-007
04/23/18         48                   859            工:XKU11892 ID:M264096
                                                     組裝: 00RM1-9732000-007
04/23/18         48                   811            工:XKU11813 ID:M263631
                                                     組裝: 00RM1-9732000-007
04/30/18         48                   763            工:12160117 ID:2470076
                                                     組裝: 00RM1-9732000-007
04/30/18         48                   715            工:09230080 ID:2222736
                                                     組裝: 00RM1-9732000-007
04/30/18         48                   667            工:09230077 ID:2222733
                                                     組裝: 00RM1-9732000-007
05/08/18         48                   619            工:12160116 ID:2470075
                                                     組裝: 00RM1-9732000-007
05/08/18         48                   571            工:11041049 ID:2348607
                                                     組裝: 00RM1-9732000-007
05/15/18         48                   523            工:12160120 ID:2470079
                                                     組裝: 00RM1-9732000-007


到期日期 Gross Reqs 計劃收料量   Proj QOH   計劃工單 明細
-------- ---------- ---------- ---------- ---------- -------------------------

05/15/18         48                   475            工:12100031 ID:2455863
                                                     組裝: 00RM1-9732000-007
05/15/18         48                   427            工:09230071 ID:2222727
                                                     組裝: 00RM1-9732000-007
05/22/18         48                   379            工:12160125 ID:2470082
                                                     組裝: 00RM1-9732000-007
05/22/18         48                   331            工:11280072 ID:2420992
                                                     組裝: 00RM1-9732000-007
05/29/18         48                   283            工:12160124 ID:2470081
                                                     組裝: 00RM1-9732000-007
05/29/18         48                   235            工:12160115 ID:2470074
                                                     組裝: 00RM1-9732000-007
06/05/18         48                   187            工:12160118 ID:2470077
                                                     組裝: 00RM1-9732000-007
06/05/18         48                   139            工:12160123 ID:2470080
                                                     組裝: 00RM1-9732000-007
06/05/18         48                    91            工:11041021 ID:2348604
                                                     組裝: 00RM1-9732000-007
06/19/18         48                    43            工:12160128 ID:2470085
                                                     組裝: 00RM1-9732000-007
06/19/18         48                    -5            工:12160119 ID:2470078
                                                     組裝: 00RM1-9732000-007
06/19/18         48                   -53            工:12160129 ID:2470086
                                                     組裝: 00RM1-9732000-007
06/26/18         48                  -101            工:12300065 ID:2522750
                                                     組裝: 00RM1-9732000-007
07/03/18         48                  -149            工:12300066 ID:2522751
                                                     組裝: 00RM1-9732000-007
07/10/18         48                  -197            工:12160127 ID:2470084
                                                     組裝: 00RM1-9732000-007
07/10/18         48                  -245            工:12160134 ID:2470089
                                                     組裝: 00RM1-9732000-007
07/24/18         48                  -293            工:01270067 ID:2601175
                                                     組裝: 00RM1-9732000-007
07/24/18         48                  -341            工:12160126 ID:2470083
                                                     組裝: 00RM1-9732000-007
07/24/18                   300        -41            採: dvtest   項次: 1
07/24/18                              459        500 工:03140002 ID:2702706
                                                     發放日期 05/15/18
07/31/18         48                   411            工:01270071 ID:2601179
                                                     組裝: 00RM1-9732000-007
07/31/18         48                   363            工:01270070 ID:2601178
                                                     組裝: 00RM1-9732000-007
07/31/18         48                   315            工:12160131 ID:2470087
                                                     組裝: 00RM1-9732000-007
08/07/18         48                   267            工:01270068 ID:2601176
                                                     組裝: 00RM1-9732000-007
08/07/18         48                   219            工:01270069 ID:2601177
                                                     組裝: 00RM1-9732000-007
08/14/18         48                   171            工:02270107 ID:2658321
                                                     組裝: 00RM1-9732000-007
08/14/18         48                   123            工:01270072 ID:2601180
                                                     組裝: 00RM1-9732000-007
08/21/18        100                    23            工:09230650 ID:2222828
                                                     組裝: 00RM1-9802000-001


到期日期 Gross Reqs 計劃收料量   Proj QOH   計劃工單 明細
-------- ---------- ---------- ---------- ---------- -------------------------

08/21/18         48                   -25            工:02270117 ID:2658323
                                                     組裝: 00RM1-9732000-007
08/21/18         48                   -73            工:02270108 ID:2658322
                                                     組裝: 00RM1-9732000-007
08/21/18                              427        500 工:03140003 ID:2702707
                                                     發放日期 06/12/18
08/25/18                   120        547            採: dvtest   項次: 2
08/28/18         48                   499            工:02270119 ID:2658325
                                                     組裝: 00RM1-9732000-007
08/28/18         48                   451            工:02270118 ID:2658324
                                                     組裝: 00RM1-9732000-007
09/04/18         48                   403            工:02270120 ID:2658326
                                                     組裝: 00RM1-9732000-007
09/04/18         48                   355            工:02270125 ID:2658327
                                                     組裝: 00RM1-9732000-007
09/11/18         48                   307            工:02270126 ID:2658328
                                                     組裝: 00RM1-9732000-007
09/11/18         48                   259            工:02270128 ID:2658330
                                                     組裝: 00RM1-9732000-007
09/11/18         48                   211            工:02270127 ID:2658329
                                                     組裝: 00RM1-9732000-007
09/17/18        100                   111            工:12100052 ID:2455881
                                                     組裝: 00RM1-9802000-001
09/20/18         48                    63            工:02270130 ID:2658332
                                                     組裝: 00RM1-9732000-007
09/20/18         48                    15            工:02270129 ID:2658331
                                                     組裝: 00RM1-9732000-007

  

thumbnail
Raymond Chin Kwie Joe, modified 8 Years ago.

Re: How to calculate MRP action message suggested due date?

Post Date: 3/14/18 (Rhodium, 825 Posts) Recent Posts
If I do understand correctly you do want to know what to do with test line 2. Expedite or de-expedite etc. On the other hand you also want to know to which date? If y assumptions are correct you can find the answers in the MRP exception report. This report should tell you what to do whith this order. Try menu 23.7 and it will tell you if you have to move an order in time and to what date. Let me know if this is the answer to your question.
thumbnail
Phill Norrey, modified 8 Years ago.

Re: How to calculate MRP action message suggested due date?

Post Date: 3/14/18 (Yoda, 1010 Posts) Recent Posts

Firstly you are looking at a custom version of the mrp inquiry.

However this report was never intended for the purpose you are asking about.

If you look at 23.6 or 23.7 then you will see if MRP has recommended a new Due Date.  You will NEVER get a suggested date for an actual PO as you have already made the order so MRP will just make an action message telling you to expidite or de-expidite the order.

If you can explain more about what you are trying to do I will be able to give you more details

David Guan, modified 8 Years ago.

Re: How to calculate MRP action message suggested due date?

Post Date: 3/15/18 (Bronze, 5 Posts) Recent Posts

Dear Raymond and Phil,

Thanks for your reply! 

Yes ,  MRP  make an action message tell me to expedite the PO dvtest Line 2 and suggest me to  advance the due date to 7/17/2018,   I want to know how MRP to calculate the suggested due date and why advance to 7/17/2018 and not 7/16/2018?  

Below is the action message, thank you! 

xxmrmprp02.p        23.8.7 MRP Action Message*        Date: 03/14/18
page:    1                    Karrie HK               Time: 19:09:28

Item Number        Date     Action Message Detail       Order Number Line/ID  Quantity Due Date 
------------------ -------- --------------------------- ------------ -------- ---------- -------- 
30G11-WC25637-001  06/11/18 expedite purchase order     dvtest       1             300.0 07/24/18
30G11-WC25637-001  07/17/18 expedite purchase order     dvtest       2             120.0 08/25/18

 

The 23.16.4 heqading in english as below for you reference.

xxmrmpiq01.p          23.16.4 MRP Detail Inquiry(原23.16)*          03/14/18

      Item Number: 30G11-WC25637-001   site: 1100              Start Date:
 PUSH SWITCH(RoHS)        按壓開關(RoHS)                       output: text

       Item Number: 30G11-WC25637-001       Qty On Hand: 1,583.0 site: 1100
PUSH SWITCH(RoHS) 按壓開關(RoHS)                     UM: EA       P/M: P
Buyer/Planner: ypurbqm   Order policy : POQ  Minimum Qty: 500   MFG LT: 0
       Mstr Sched: YES    Order Period: 7    Maximum Qty: 0     Pur LT: 70
 MRP Required : NO       Time Fence : 0              MPQ: 500   Ins LT: 0
    Plan Orders: YES    Safety Time: 5       Order Qty: 0      Inspect: NO
     Issue Policy: YES    Safety Stock: 0     Yield%: 100.00%   Cum LT: 0

thumbnail
Raymond Chin Kwie Joe, modified 8 Years ago.

Re: How to calculate MRP action message suggested due date?

Post Date: 3/15/18 (Rhodium, 825 Posts) Recent Posts
The question is simple but the calculations can be quite complex, many factors are taken into account. The date when the inventry "dives" under zero, the purchase lead time, inspections times, and espcecially the MRP start weekday (MRP control file). In fact all the item planning parameters (1.4.7) and some general settings like calendars and mrp control file (23.24) have influence on the calculation. Now this does not help you much but there is no really easy way to understand MRP. The concept is not unique for QAD, it is decided by MRP rules. To understand I would suggest to review some traning manuals and see how the MRP due dates are calculated (page 13). If you have very specific MRP questions you may also visit an MRP forum like this one.
thumbnail
Phill Norrey, modified 8 Years ago.

Re: How to calculate MRP action message suggested due date?

Post Date: 3/15/18 (Yoda, 1010 Posts) Recent Posts

OK the answer is actually quite simple.  You have a Safety LT of 5 days.  In QAD that is actually working days so it equates to 7 calendar days.

MRP will ALWAYS suggest you move existing orders before creating new Orders so if we follow the logic of the action messages it firstly tells you to move Line 1 of the PO to 06/11.  If you did that then you would not go negative again until 07/24. So it wants to pull the second line forward as well to ensure you don't go negative and because you have 7 calendar days Safety LT it means you need to receive it (DUE Date) 7/17.

due demand supply  Proj QOH  
5-Jun 48 0 187  
5-Jun 48 0 139  
5-Jun 48 0 91  
11-Jun   300 391 dvtest ln 1
19-Jun 48 0 343  
19-Jun 48 0 295  
19-Jun 48 0 247  
26-Jun 48 0 199  
3-Jul 48 0 151  
10-Jul 48 0 103  
10-Jul 48 0 55  
17-Jul   120 175 dvtest ln2
24-Jul 48 0 127  
24-Jul 48 0 79  

 

David Guan, modified 8 Years ago.

Re: How to calculate MRP action message suggested due date?

Post Date: 3/18/18 (Bronze, 5 Posts) Recent Posts

Dear Raymond and Phill,   

Thanks for your reply! 

 MRP will ALWAYS suggest you move existing orders before creating new Orders, 

First time Project-Qty-OnHand go negative is 6/19/2018, so MRP suggest us move PO Dvtest Line 1 to 6/18/2018 prior 6/19/2018, 
and the suggest date is 6/11/2018 due to 7 calendars safety time .
And second time Project-Qty-OnHand go negative is 7/24/2018, so MRP suggest us move the second supply PO Dvtest Line 2 to 7/23/2018,
and the suggest date should is 7/16/2018 due to 7 calendars safety time, but it is 7/17/2018. 

i would like to know the why is 7/17/2018 not 7/16/2018. thanks!

thumbnail
Raymond Chin Kwie Joe, modified 8 Years ago.

Re: How to calculate MRP action message suggested due date?

Post Date: 3/19/18 (Rhodium, 825 Posts) Recent Posts

@Phil: good calculation!I 

Regarding the question, I think Phil answered this, if you take the 24th then thedate is the 17th.Probablythe 23rd is suggested because the 24th of July is a saturday. If you move the supply to the 23rd it may well suggest the 16th. btw, if you want to understand these mechanisms you will have to read & practice. Unless you have a Phil around to help you :-)

David Guan, modified 8 Years ago.

Re: How to calculate MRP action message suggested due date?

Post Date: 3/20/18 (Bronze, 5 Posts) Recent Posts

Dear Raymond and Phill,

Thanks for your help for this topic!

7/24/2018 is not saturday. 

There are two demand in 7/24/2018, and the supply can satify the first demand but can not satify the second, 

so maybe the MRP calculate the suggested due date is start from 7/24/2018, and move  it forward 7 calendar days to 7/17/2018.

thumbnail
Phill Norrey, modified 8 Years ago.

Re: How to calculate MRP action message suggested due date?

Post Date: 3/21/18 (Yoda, 1010 Posts) Recent Posts

Sometimes following dates can be complicated.  Do you have any holidays set up in your calendar for example.

What I would suggest is that you first remove the SLT so you can see the actual calculation for due dates with no interferance.  This should help make it easier to understand.

And then change it to one day and run again.  Repeat this until you get to your back to your 5 working day SLT.

It is complicated because of the caculation to change from work days to calendar days co by doing it one at a time you will see what happens

David Guan, modified 8 Years ago.

Re: How to calculate MRP action message suggested due date?

Post Date: 4/9/18 (Bronze, 5 Posts) Recent Posts

Dear Phill and Raymond,

With your help, my MRP problem has been solved, thank you very much!

thumbnail
Phill Norrey, modified 8 Years ago.

Re: How to calculate MRP action message suggested due date?

Post Date: 4/9/18 (Yoda, 1010 Posts) Recent Posts
Your welcome.  Glad I could help!

Message place holder