How is calculated the total cumulative time of a manufactured item
Sylvain Gueguen, modified 3 Years ago.
How is calculated the total cumulative time of a manufactured item
Post Date: 6/21/20 (Bronze, 3 Posts) Recent PostsHello
I have several articles manufactured with a "cumulative lead time" at zero, this is not normal.
I'm looking to understand how this value is calculated (Cum LT).
I use 2013EE, i see this information in Item Planning Data
Could you help me ? please
Thank you
Phill Norrey, modified 6 Years ago.
Re: How is calculated the total cumulative time of a manufactured item
Post Date: 6/22/20 (Yoda, 1010 Posts) Recent PostsHave you run the Cumulative lead time roll up?. It starts at the bottom (Purchased Items) and uses the Purchase LT, then at the next level it uses the Manufactured time (*1.4) because MLt is in working days not calendar, and then keeps repeating up the chain always adding the longest CLT from the level below.
Phill Norrey, modified 6 Years ago.
Re: How is calculated the total cumulative time of a manufactured item
Post Date: 6/22/20 (Yoda, 1010 Posts) Recent PostsHave you run the Cumulative lead time roll up?. It starts at the bottom (Purchased Items) and uses the Purchase LT, then at the next level it uses the Manufactured time (*1.4) because MLt is in working days not calendar, and then keeps repeating up the chain always adding the longest CLT from the level below.